CIP Projects

Please check this page for updates on current and upcoming road construction.

Click here for Road Work Map

Street Improvement Projects

March 1st - April 30th

  • Battaglia Road reconstruction between Sunshine Blvd and La Palma Rd. Battaglia Rd will be closed from March 31 through April 9.

March 26th - April

  • HSIP Jimmie Kerr (Frontier St) Rumble Strip Project from Casa Grande Ave (in Casa Grande) east to SR87. Frontier St will have lane restrictions in Eloy City Limits from April 5 through April 9.

March 23rd through April 23rd

  • Chip Seal Project in Toltec Unit 9 and Estrella Rd from Hanna Rd to Shedd Rd. click here for map.
  • Fog Seal Project on Sunland Gin Rd from Hanna Rd to Houser Rd. 
  • Chip Seal Project on Sunland Gin Rd from Phillips Rd to Harmon Rd.


Airport Improvement Projects

The Airport Taxiway ’A’ Relocation and Drainage Improvements started in September 2020 and is scheduled to finish in April 2021. Click here for phasing exhibits.

Airport Lighting Rehab Project is scheduled to begin in May and be completed in June 2021.

If you have any concerns, please contact Tammy Valadez Paz at 520-464-3166.